$$ % Define your custom commands here \newcommand{\bmat}[1]{\begin{bmatrix}#1\end{bmatrix}} \newcommand{\E}{\mathbb{E}} \newcommand{\P}{\mathbb{P}} \newcommand{\S}{\mathbb{S}} \newcommand{\R}{\mathbb{R}} \newcommand{\S}{\mathbb{S}} \newcommand{\norm}[2]{\|{#1}\|_{{}_{#2}}} \newcommand{\pd}[2]{\frac{\partial #1}{\partial #2}} \newcommand{\pdd}[2]{\frac{\partial^2 #1}{\partial #2^2}} \newcommand{\vectornorm}[1]{\left|\left|#1\right|\right|} \newcommand{\abs}[1]{\left|{#1}\right|} \newcommand{\mbf}[1]{\mathbf{#1}} \newcommand{\mc}[1]{\mathcal{#1}} \newcommand{\bm}[1]{\boldsymbol{#1}} \newcommand{\nicefrac}[2]{{}^{#1}\!/_{\!#2}} \newcommand{\argmin}{\operatorname*{arg\,min}} \newcommand{\argmax}{\operatorname*{arg\,max}} \newcommand{\dd}{\operatorname{d}\!} $$

Tipping the block off the riser: deriving the departure ramp

The disk must change its command from the force that holds the block to the force that tips it, in steps small enough for the realizer to execute accurately. A schedule chosen from margins at one nominal state failed the certificate over the whole set of states; the ramp is now derived with the set-based certificate itself as the constraint.

Status of November 25, 2026. Every number is from a committed record in RobotControlLab/certified-contact-graphs (private), branch feat/certify-canonical-front, and the decision log. The derivation described here is running; its results are pending.

The physical situation

Early in the canonical route the block rests flush against the riser (the step’s vertical face), held there by the disk. The next piece of the route, F6, tips it: the block leaves that rest and starts to rotate. (In the paper’s drawings +x points to the left, and the step is on the left of the block.)

The disk holds the block with one force and tips it with another, the tipping law’s. Its command cannot jump from one to the other in a single step: the realizer executes a jump in the command with a force error that grows with the size of the jump, and every certificate downstream has to absorb that error. So the command moves along a ramp. A parameter σ runs from 0 (the hold) to 1 (the tipping law), and the disk is commanded the corresponding blend at each step. For small σ the block stays at rest; at some σ short of 1 it breaks away and starts to tip.

Two regimes, two certificates

The certificate is split at break-away:

  • Rest steps. Every command up to the last rest command σᵣ must be certified at rest over the whole box of states the block can be in: every motion other than “stays at rest” is excluded on every piece of a branch-and-prune split, with the disturbance widened by that step’s force error.
  • The break-away step. At the break-away command σ_b the departure certificate must show that leaving rest by the planned tipping motion is the only way out, with a no-stick margin of at least the force error, and the block’s tilt rate at the next step must stay below a derived slip cap, s′ₘₐₓ = 0.18350 rad/s. Faster, and the block’s floor corner slips, and the block misses the entry of the next certified piece.

The switch-error envelope

The realizer’s force error at a command jump Δ, measured on simulated departures (one-sided 95/95 bound):

Command jump Δ 0.125 0.25 0.333 0.5 0.7 0.943
Switch error e(Δ) (mN) 5.17 10.36 13.08 19.68 27.47 37.22

It grows steadily, about 39 mN per unit of σ. The two regimes pull against each other through it: a big break-away jump Δ_b = σ_b − σᵣ means a big error e(Δ_b), which every rest step must absorb and the break-away margin must exceed; small jumps keep the error small but need many steps.

Two schedules that did not work

  • Greedy (the largest admissible step each time): its first step reaches σ = 0.738, where the block rests with a margin equal to the 37.2 mN error of the jump that would follow. Breaking away from there needs a 37.2 mN D2 margin, which holds only at σ = 0.998, where the next tilt rate (0.208 rad/s) exceeds the cap. No feasible completion.
  • Minimax on the measured grid (the smallest largest step, Δ = 0.125, error 5.17 mN): rest steps at σ = 0.125, …, 0.75 and 0.8499, break-away at 0.9424. The hold and the rest steps up to σ = 0.75 are certified. The step at σ = 0.8499 is not.

The lesson: a margin at one point is not a margin over the set

At σ = 0.8499 the rest force at the nominal state clears its bound by 5.23 mN, against a widening of 4.91 mN: 1.06 slack units, which passes the “at least one measured slack” rule. Yet the rest check over the whole box of states fails, at branch-and-prune depth 4 and again at depth 5. One motion class stays undecided, and its braking test barely moves with the extra depth (−55.96 at depth 4, −55.10 at depth 5).

The nominal state is one point of the box. Other states in the box have less rest force, and a 0.3 mN spare at the nominal point does not cover them. A deeper split tightens the enclosure, but it cannot create a margin that the set itself does not have.

A pointwise margin of at least one slack is necessary for a set-based certificate. It is not sufficient.

The derivation (decision 159 (a′))

So the ramp is derived with the set-based rest check itself as the constraint, with no grid choice and no hand-picked spacing:

  1. Break-away for each error level. For each measured jump Δⱼ of the envelope, σ_b is the smallest command past the rest edge whose certified D2 margin is at least e(Δⱼ) and whose certified next-step tilt rate is at most s′ₘₐₓ.
  2. The rest edge by bisection. The level is feasible if the whole-box rest check (depth 4) passes at σ_b − Δⱼ with the disturbance widened by e(Δⱼ). The last rest command σᵣ is found by bisection on that box check.
  3. The earlier rest steps are equal and no larger than Δ_b = σ_b − σᵣ, so each one’s error is at most e(Δ_b), the widening already certified.
  4. After break-away the steps follow the slip cap until the tipping law takes over.

Then, as for any schedule: the switch error is re-measured on the derived ramp, the full split certificate (rest, then break-away) is run, then the take-off, the tip funnel’s entry and F6’s junction into the next piece. If no level is feasible, that is the result: the tipping law cannot be certified for F6 with this realizer.

Pending: the derived σᵣ, σ_b and schedule, and the certificates that follow. Certified so far, under the earlier schedule: the hold and the ramp steps up to σ = 0.75.